Amperage upgrade 2027: the price rises by 50%, here is what you pay per amp
Buying an electric car, and your electrician says your current connection will not be enough? Then now is the time to pay attention: from 1 January 2027 an amperage upgrade costs 50% more. Under the decision published by MEKH, the Hungarian energy regulator, on 16 November 2026, the price of an amperage upgrade will be HUF 5,850 + VAT per amp instead of HUF 3,900 + VAT. Below you will find what this means in forints, how many amps are free, and when a smaller upgrade is enough. (As of November 2026)

How much more will an amperage upgrade cost from 2027?
From 1 January 2027 the low-voltage connection base fee is HUF 5,850/A + VAT, which is about HUF 7,430 per amp gross. Today it is HUF 3,900/A + VAT, about HUF 4,950 gross. The fee has barely changed since 2016, and now it rises by 50% in one step.
You pay the fee for the additional amps, that is, for how much more current you request after the upgrade than before. Some typical upgrades for a detached house:
Upgrade | Additional | In 2026 | From 2027 |
|---|---|---|---|
From 1×32 A to 3×16 A | +16 A | approx. HUF 79,000 | approx. HUF 119,000 |
From 1×32 A to 3×25 A | +43 A | approx. HUF 213,000 | approx. HUF 319,000 |
From 1×32 A to 3×32 A | +64 A | approx. HUF 317,000 | approx. HUF 475,000 |
The table shows only the connection base fee paid to the distributor, gross. The electrician's work, any changes to the meter point and any line fee come on top.
How many amps are free?
You do not have to pay the base fee if the sum of the currents requested per phase is at most 32 A. So 1×32 A is free, but 3×16 A is not, because that adds up to 48 A. Many people believe 3×32 A is free, but that is a myth.
That is why every amp counts. Whatever you request above the 32 A allowance, you pay for. If you have 1×32 A now and upgrade to 3×16 A, you pay for 16 additional amps, not 48. If you go to 3×32 A, you pay for 64 amps.

How do you work out the fee for your own upgrade?
It takes three steps. Add up the amps per phase of your current connection, then do the same for the planned connection. The difference between the two is the additional amps, and you multiply that by about HUF 7,430 gross.
An example: if you have 3×16 A now (48 A in total) and would upgrade to 3×25 A (75 A in total), that is 27 additional amps. At 2027 rates this comes to about HUF 201,000 gross. Going from 3×16 A to 3×32 A would be 48 amps, or about HUF 357,000.
If you have 32 A or less in total today (for example 1×32 A), the starting point is 32 A, because that much is free. The exact amount is set out in the distributor's technical and economic information letter, and the calculation is only there to show you the order of magnitude in advance.
When do you also have to pay a line fee?
You only pay a public line fee if the distributor has to build new network because of your request. From 2027, at low voltage, this is HUF 7,950/m for an overhead line and HUF 12,750/m for an underground cable, excluding VAT. This is also 50% more than now.
A certain length is free:
up to 32 A: 100 m of overhead line or 50 m of underground cable,
above 32 A: 50 m of overhead line or 25 m of underground cable.
Whether you have to pay a line fee is stated in the distributor's technical and economic information letter.
Do you need an upgrade for an electric car at all?
Not always. If the charger adjusts the charging current to the household's current consumption, it does not exceed the main fuse, and a smaller upgrade is often enough. This is what Dynamic Load Management does.
Charging a car is a long, heavy load. If the charger always drew the maximum current, the connection would have to be sized for the moment when the oven, the washing machine and the heat pump are also running. That is why a large upgrade often comes up. The other way is for the charger to adapt to the house. Voltie Dynamic Load Management monitors the household's consumption phase by phase and always gives charging only what is left. That way the main fuse does not trip.
That is why a smaller upgrade is often enough. If 3×16 A is enough for you instead of 3×32 A, that is 48 amps less. At 2027 rates, that is a difference of about HUF 357,000 gross in fees.
Dynamic Load Management requires the VoltieMeter, available separately. The charger's maximum charging current is set by the electrician during installation.
Dynamic Load Management is a feature of the Voltie smart charger, alongside the solar charging modes.
Is it worth upgrading this year?
If you were going to upgrade anyway, it is worth looking into it now. What we do not know for certain, however, is whether the old fee depends on the date of the request, the date the contract is signed or the date of payment. Neither the MEKH decision nor the relevant regulation says.
Before you rely on this, ask your own electricity distributor for the exact rule.
How does an amperage upgrade work?
The request has to be submitted to the distributor, and this is typically done by your electrician. The distributor sends a technical and economic information letter setting out what needs to be changed and the fee to be paid. We describe the steps in detail in our article on what to do for an amperage upgrade.
If the upgrade involves bigger changes, our article on upgrading your electrical supply for an electric car also tells you what to look out for.
How do you know what connection you need?
This is decided by your main fuse, the other appliances in the house and your car together. If you do not know whether your current connection is enough, request a quote on voltie.eu. Give us the rating of your main fuse and the type of your car, and we will tell you what connection to plan for.
Sources
As of November 2026. The fees may change every year.
Frequently asked questions
From 2027 the connection base fee is HUF 5,850/A + VAT, about HUF 7,430 gross per amp. An upgrade from 1×32 A to 3×16 A therefore costs about HUF 119,000 gross, excluding the electrician's work.
Would you like a quote for your charger?